Legal blog > Construction > Construction lien in the absence of evidence of added value

Construction lien in the absence of evidence of added value

In the absence of adequate proof of added value, the contractor cannot benefit from a legal mortgage.

«The one to whom everyone gives second place deserves the first»
Jonathan Swift

A creditor, like a contractor, must evaluate whether the funds invested in a building for the purpose of work generate an equivalent increase in value.

Thus, a company, after acquiring a building for $695,000, mortgages it in favor of a creditor for an amount of $750,000. A contractor carries out various work on this building and, due to non-payment by the company, registers legal liens on the property totaling $558,000. Following forced abandonment procedures, the building is sold under judicial control for the amount of $675,000.

The legal liens are then given first priority, leaving the initial mortgage creditor with practically nothing. Dissatisfied, the latter turns to the Court* and reminds it that:

  • normally, the legal construction lien takes priority over a previously registered conventional mortgage, but "only to the extent of the increase in value given to the property";
  • the increase in value is unique for all the work;
  • the increase in value requires a comparative analysis of the value of the property before and after the work;
  • the value of the property is determined at the end of the work and not at the time of the sale.

After this reminder, the court concludes that the evidence on record demonstrates that the specificity of the work performed results in "a lack of increase in value, even requiring costs to remove certain elements", which means a negative value for the buyer (of the property).

The court orders that the contractor's legal liens be removed "in the absence of adequate proof of an increase in value".

As the Latin proverb says, "the burden of proof lies with he who asserts and not he who denies".

*CA 500-09-021702-113

François Forget, notary and legal advisor as well as the entire Notaire-Direct team, are at your service to ensure the preparation of your legal documents and answer all your legal questions.
Purchasing a building and unequal down payments by spouses
Me François Forget - October 15, 2019
A multitude of unmarried couples are building a life project that often begins with the purchase of a home....
Did the husband become rich at the expense of his wife during their common life?
Me François Forget - March 20, 2011
The Civil Code does not subject couples who simply live together to the family patrimony and a matrimonial regime....
A contract is like a sauce, you have to balance the ingredients!
Me François Forget - March 31, 2004
When there is doubt, a contract is interpreted in favor of the party who assumed the obligation.